EMPIRICAL STUDY ON THE INFLUENCE OF PROCUREMENT METHODS ON LAST PLANNER® SYSTEM IMPLEMENTATION

Daniel, Emmanuel and Pasquire, Christine and Dickens, Graham and Ramesh, Marasini. (2018). EMPIRICAL STUDY ON THE INFLUENCE OF PROCUREMENT METHODS ON LAST PLANNER® SYSTEM IMPLEMENTATION. In: Proceedings of the 26th International Group for Lean Construction. India Institute of Technology Madras, Chennei, India, pp. 681-690.

[img]
Preview
PDF
Daniel et al. 2018 - Empirical Study on the Influence of Procurement Methods on Last Planner System Implementation.pdf - Published Version

Download (625kB) | Preview

Abstract

Previous studies have examined various factors that influence the implementation of the Last Planner System (LPS) in construction projects. However, there is limited documented evidence on the influence of procurement methods on the implementation of the LPS. The aim of this study, therefore; is to understand the influence of some selected procurement methods on the implementation of the LPS using case study approach. Three in-depth case studies were conducted on building and highways projects in the UK. The projects were managed with the LPS principles with dissimilar procurement methods. In addition to document analysis and physical observation, 28 in-depth-interviews were conducted. The investigation shows that the prevailing traditional mindset exhibited by the designers in the traditional design bid build (DBB) influences the quality of promises and commitments that could be made during the lookahead planning. From the study, it seems no single procurement method is a sure way to the full application of the LPS process on a project. The study observes that irrespective of the procurement route used, a mindset change towards collaboration among the different stakeholders on the project is fundamental to successful LPS implementation. For instance, on projects where DBB was used and the subcontractors were in framework agreement, the LPS implementation worked well among the subcontractors. The study recommends that the procurement approach to be used on LPS projects should not be too firm, but lithe enough to integrate collaborative working among the different stakeholders on the project for a smooth workflow.

Item Type: Book Section
Subjects: TECHNOLOGY > Construction
Faculties: Faculty of Creative Industries > School of Art and Design > School of Fashion
Depositing User: Emmanuel Daniel
Date Deposited: 21 Jul 2018 16:59
Last Modified: 21 Jul 2018 16:59
URI: https://ssudl.solent.ac.uk/id/eprint/3895